NEWMAP Delivering Project Development Objectives (PDO)

Nigeria Erosion and Watershed Management Project

NEWMAP Delivering Project Development Objectives (PDO)

July 28, 2016 featured FPMU News Recent News 0

Three years and more, NEWMAP has continued to impact positively on the lives of many in and around the project sites and states.
Currently civil works in the first 21 gully erosion sites across the first mover states of Abia, Anambra, Cross River, Ebonyi, Edo, Enugu and Imo are at advance stages of completion after the payment of over 821m as compulsory compensation to 984 Project Affected Persons (PAPs) directly affected by the ongoing construction works across the states.
(Please see dates table @ www.newmap.gov.ng)

Atakpa Gully Erosion Site, Cross River State

Atakpa before        Atakpa Now

Before Intervention                                                After Intervention

Queen Ede site, Edo State

Edo State

After Intervention

After Intervention

Table 1: PROGRESS/PROJECT STATUS: IMPLEMENTATION CONTRACT AWARDED.

S/NO              STATE NO of Sites awarded contract                Name of site         LGA % WORK DONE         REMARKS
1 ABIA 3 Amuda Achara

Amuzukwu

Umuezeukwu

Umuahia North

Isialangwa North

Umumeochi

 

15.0%

50.0%

90.0%

 

Work is progressing

 

 

2. ANAMBRA 4 Amachalla

Omagba Onitsha

St Thomas Aquinas/Neroz Plaza

Umudunu Abagana

Awka South

Onitsha north

Awka North

Nijikoka

93.0%

63.0%

82.0%

45.0%

Satisfactory
3. CROSS RIVER 5 Atakpa

Edim Etop

Ikot Anwatim

Ikot Ekpo

Nyagassang

Calabar South

Calabar Municipal

Calabar Municipal

Calabar Municipal

Calabar Municipal

86.1%

84.6%

71.1%

73.5%

60.4%

Satisfactory.

Work progressing well

4. EBONYI 1 Nguzu Edda Afikpo South 73.0% Work progressing well
5. ENUGU 2 9th Mile corner

Ajali Water works

Ameke Ngwo

Udi

82.1%

89.8%

Satisfactory
6. EDO 3 Auchi

Ekehuan

Queen Ede

Etsako West

Egor

Ikpobaokha

80.0%

80.0%

81.3%

Progressing of work is satisfactory
7 IMO 3 Eziala Obizi

Iyiuzo Ihioma

Umueshi

Ezinhitte Mbaise

Orlu

Ideato South

90.0%

90.0%

78.05

Work going on well
21

 

 