UPDATE ON IMPLEMENTATION OF INITIAL 21 SITES AND TABLE OF NEW SITES

Nigeria Erosion and Watershed Management Project

UPDATE ON IMPLEMENTATION OF INITIAL 21 SITES AND TABLE OF NEW SITES

February 2, 2017 Abia State Akwa Ibom State Anambra State Borno State Cross River State Delta State Ebonyi State Edo State Enugu State FPMU Gombe State Imo State Implementation Status and Results Report Kano State Katsina State Kogi State Nasarrawa State News Niger State Oyo State Plateau State Recent News Sites Under Constructions Sokoto State 0

% IMPLEMENTATION OF INITIAL 21 SITES IN SEVEN (7) OLD NEWMAP STATES.

S/NO                   STATE                        PROJECT SITE PERCENTAGE OF WORK DONE (%) REMARKS  
1 ABIA Amuda Achara

Amuzukwu

Umuezeukwu

21.0

55.0

96.0

Amuda Achara is low due to redesign and contractors low capacity.  
2. ANAMBRA Amachalla

Omagba Onitsha

St Thomas Aquinas/Neroz Plaza

Umudunu Abagana

97.0

74.0

92.0

56.0

   
3. CROSS RIVER Atakpa

Edim Etop

Ikot Anwatim

Ikot Ekpo

Nyagassan

99.8

100.0

93.4

100.0

84.2

   
4. EBONYI Nguzu Edda 78.6    
5. ENUGU 9th Mile corner

Ajali Water works

96.0

100.0

   
6. EDO Auchi

Ekehuan

Queen Ede

80.0

45.0

93.0

Ekehuan is 45% compared to the recent request for additional works  
7 IMO Eziala Obizi

Iyiuzo Ihioma

Umueshi

99.5

99.8

94.6

   

LIST OF NEWMAP SITES UNDER DESIGN/REVIEW

S/NO STATE PROJECT NAME STATUS WITH FQCEDF COMMENTS
1 ABIA Umuogele

Umuda Isingu/Umuagu Ibeku

Aba flood (Four ponds)

Completed

Completed

Review on going.

Cleared by the Bank

Cleared by the Bank

2 ANAMBRA Abidi Village

Enugu Ukwu

Ugama Obosi

Ire Obosi

Ndiagu Ikenga

Nnnewichi

Nkpor Fly over

Ojoto

Nankah Okoh

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

All Eight (8) sites have been cleared by the Bank.

 

 

 

 

 

 

Review on going by the Bank.

3 CROSS RIVER Ikot Nkebre

Lemna Agric Road

Igaba

Ikot Uduak

Okuku

Completed

Completed

Cost option cleared

Review ongoing

Cost Option cleared

 

 

Ikot Nkebra and Lemna Agric cleared by the Bank. With major comments to be addressed by the SPMU.

 

 

 

 

4 EBONYI Ebia River

Odunukwe Nkaliki

Iyiudele River

Iyiukwu Abakaliki

Asu Umunaga

Oferekpe

Abakaliki Old water works

Completed

Completed

Completed

Completed

Review Ongoing

Review Ongoing

Review Ongoing

All Four (4) completed have been cleared by the Bank.

 

 

 

 

 

5 EDO Gapiona

Ibore Esan

Ewu Esan

New Urora

Fugar Agenebode

Ambrose Alli Uni

Edo College

Ogiso Osunde

Emu Ohuda

Igbe Quarters

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

All the ten sites cleared by the Bank. Some with minor issues to address by the SPMU.

 

6 ENUGU Agbaja Ngwo

Enugu Nwgo (4 fingers)

Umuavulu-Abor

Odi Ozalla

Imilike Etiti

Ngene Owelle

Onuiyi

Completed

Completed

Completed

Completed

Cost option and feasibility studies cleared.

All four cleared by the Bank with minor comments to be addressed by the SPMU.

 

 

7 IMO Urualla

Umueze Obazu

Ibeafor

Completed

Completed

Completed

 

Uruala and Obazu sites have been cleared by the Bank.Urualla is at the bidding stage.

 

8. Akwa Ibom Anua Ravine

Etim Umana

St Luke’s Hospital

Completed

Completed

Review on going

Anua Ravine and Etim Umana are under review with the Bank.

 